Construction

An image of Oakton College's Ten Hoeve Construction.

Small Business Development Center and Educational Foundation (at Des Plaines TenHoeve Center)

Stakeholder(s):

Educational Foundation, Small Business Development Center (SBDC)

Percent Complete:

99%

Project Start:

12/1/2023

Project Completion:

06/28/2024

The punchlist is currently being completed by the contractor. Department moves are on schedule for the week of July 8.

An image of Oakton College's Des Plaines campus office rennovations.

Liberal Arts, Academic Affairs and Institutional Research Office Renovations (Des Plaines Floor 2)

Stakeholder(s):

Office of Academic Affairs, Office of Liberal Arts, Office of Institutional Research

Percent Complete:

40%

Project Start:

04/08/2024

Project Completion:

01/17/2025

Phase 1 office suite renovations for Liberal Arts and Institutional Research are nearing completion. Furniture is expected to arrive during the week of July 8. Department moves (Liberal Arts and Institutional Research) are tentatively scheduled for the week of July 15.

Department moves are tentatively planned for 7/29-8/9.

An image of the Skokie  Library Learning Commons Construction update.

Skokie Library Learning Commons

Stakeholder(s):

ADRC, Learning Center, Library, Testing Center, TRIO

Percent Complete:

90%

Project Start:

12/18/2023

Project Completion:

07/08/2024

The contractor is working to install finishes throughout both floors. Construction is planned to be substantially complete on the week of July 8. The furniture is scheduled for installation week of July 15. Department moves are tentatively planned for the weeks of July 29 and Aug. 9.

An image of the new door and hardware replacement at Oakton College.

Door and Hardware Replacement

Percent Complete:

10%

Project Start:

TBD

Project Completion:

TBD

Kluber Architects is working on construction documents for phase 1, which entails repairs and replacement to exterior doors across both campuses. Construction dates will be established upon completion of construction documents and bidding process.

An image of updated Signage at Oakton College.

Signage Update

Percent Complete:

99%

Project Start:

11/22/2021

Project Completion:

07/26/2024

All interior signs have been installed and corrections to signage are complete. All exterior signage is installed except for new signage at door 5 at Des Plaines, which will be installed in July 2024.

An image of the master construction plan at Oakton College.

Landscape Master Plan Project

Percent Complete:

63%

Project Start:

10/23/2023

Project Completion:

07/26/2024

Work is progressing across both campuses. Door 5 at Skokie is expected to remain open throughout construction. 

Work at door 5 has begun and is scheduled to be completed by July 12. Work at door 5 will include demolition and replacement of concrete, construction of new benches and installation of new landscaping.

An image of the Oakton College Leaf on a grey background.

Baseball Field Renovation

Stakeholder(s):

Athletics Department

Percent Complete:

40%

Project Start:

Spring 2023

Project Completion:

Fall 2024

Field demolition and sub-grading is completed. Surveying crews are verifying surface grade elevations and irrigation system installation has begun.